Bronx Street Tree Planting FY21

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement trees in street tree beds that have been previously excavated and backfilled with soil and compost in the Bronx.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: January 2021
Projected Completion Date: April 2021
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: November 2021
Completion Date: July 2021

Construction

Start Date: September 2021
Projected Completion Date: January 2022

Understand how we build parks.

Funding

Total Funding: $101,000

Location

Various locations in the Bronx

Project Staff

Contact NYC Parks about this project

Last updated: 11/26/2021

Was this information helpful?