Marine Park Forest Restoration

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore native species habitat within forested natural areas in Marine Park.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: January 2021
Projected Completion Date: October 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Marine Park , Brooklyn
East of Gerritsen Avenue between Bartlett Place and Lois Avenue

 

Project Staff

Contact NYC Parks about this project