Coney Island Lifeguard Station Electrical Service Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct electrical service to the lifeguard station at Coney Island Boardwalk.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: December 2020
Projected Completion Date: February 2021
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: October 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Coney Island Beach & Boardwalk , Brooklyn
Coney Island Boardwalk near Coney Island Avenue

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 02/25/2021