Udall's Park Preserve Forest Restoration

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will restore native species habitat within forested natural areas in Udall's Park Preserve.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: January 2021
Projected Completion Date: January 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Udall's Park Preserve , Queens
40th Avenue between Douglas Road and Little Neck Parkway

 