Sol Bloom Playground Basketball Court Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the basketball court in Sol Bloom Playground.

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Start Date: January 2021
Projected Completion Date: January 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Sol Bloom Playground , Manhattan
West 91st Street and West 92nd Street between Columbus Avenue and Central Park West

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/01/2021