Aqueduct Walk Reconstruction at West Burnside Avenue

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct an ADA-accessible entrance, pathways, a plaza, stairs, retaining walls, park security lighting and landscaping at Aqueduct Walk.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: June 2021
Projected Completion Date: December 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Aqueduct Walk , Bronx
East of University Avenue between West 180th Street and West Burnside Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project