  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the track, synthetic turf field, tennis courts, and playground at Detective Keith L. Williams Park. The work includes new synthetic turf, new track, bleachers, tennis court pavements, play equipment for 2-5 and 5-12 years old, spray shower, swings, seating areas, security lighting, fencing, drainage, electrical work, water supply and planting.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: March 2021
Projected Completion Date: March 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Detective Keith L Williams Park , Queens
173rd Street and between 104th Avenue and 106th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande