Kimlau Square Arch Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the arch in Kimlau Square.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks is continuing to develop the documents to build this project and applying for necessary permits.

Project Timeline

Design

Start Date: January 2021
Projected Completion Date: August 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Kimlau Square , Manhattan
Chatham Sq., Oliver St. and East Broadway

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/15/2022