Brooklyn Street Tree Planting FY21 - Community Boards 2-3

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 2-3 in Brooklyn.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2020
Projected Completion Date: May 2021
Completion Date: November 2020

Procurement

Start Date: November 2020
Projected Completion Date: August 2021
Completion Date: June 2021

Construction

Start Date: September 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $500,000

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 05/25/2022