Brooklyn Street Tree Planting FY21 - Community Boards 2-3
-
100% complete
-
100% complete
-
0% complete
This project will plant new and replacement trees in Community Boards 2-3 in Brooklyn.
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Start Date: October 2020
Projected Completion Date:
May 2021
Completion Date:
November 2020
Procurement
Start Date: November 2020
Projected Completion Date:
August 2021
Completion
Date:
June 2021
Construction
Start Date: September 2021
Projected Completion Date:
May 2022
Understand how we build parks.
Funding
Last updated: 05/25/2022