Bronx Street Tree Planting FY21 - Community Boards 5-8
-
100% complete
-
100% complete
-
0% complete
This project will plant new and replacement trees in Community Boards 5-8 in the Bronx.
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Start Date: October 2020
Projected Completion Date:
May 2021
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
September 2021
Completion
Date:
July 2021
Construction
Start Date: November 2021
Projected Completion Date:
July 2022
Understand how we build parks.
Funding
Last updated: 05/25/2022