Arden Woods Trail Construction
-
100% complete
-
5% complete
-
0% complete
This project will construct hiking trails at Arden Woods.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: March 2020
Projected Completion Date:
September 2020
Completion Date:
July 2020
Procurement
Start Date: July 2020
Projected Completion Date:
March 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Arden Woods
, Staten Island
Between Arthur Kill Road and Woodrow Road
Project Staff
Contact NYC Parks about this projectLast updated: 02/26/2021