Arden Woods Trail Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct hiking trails at Arden Woods.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: March 2020
Projected Completion Date: September 2020
Completion Date: July 2020

Procurement

Start Date: July 2020
Projected Completion Date: March 2021
Completion Date: June 2022

Construction

Start Date: August 2022
Projected Completion Date: July 2023

Understand how we build parks.

Funding

Total Funding: $567,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Arden Woods , Staten Island
Between Arthur Kill Road and Woodrow Road

 

Project Staff

Contact NYC Parks about this project

Last updated: 09/26/2022