Paerdegat Athletic Center Boiler Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the boiler at the Paerdegat Athletic Center.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: February 2020
Projected Completion Date: February 2021
Completion Date: March 2021

Procurement

Start Date: March 2021
Projected Completion Date: November 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Paerdegat Basin Park , Brooklyn
1500 Paerdegat Avenue North

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/17/2021