Citywide Tree Guard Installation FY21

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will install tree guards at street trees citywide.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: December 2019
Projected Completion Date: May 2020
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: August 2022

Construction

Start Date: September 2022
Projected Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $991,000
Funding Source: Mayoral

Location

Various locations citywide

Project Staff

Contact NYC Parks about this project

Last updated: 10/04/2022