Clove Lakes Park World War II Memorial Ice Rink Slab and Header Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the ice rink slab and header at the World War II Memorial Ice Rink in Clove Lakes Park.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: February 2021
Projected Completion Date:
May 2021
Completion Date:
June 2021
Procurement
Start Date: June 2021
Projected Completion Date:
March 2022
Adjusted Completion
Date:
November 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Clove Lakes Park
, Staten Island
1305 Victory Boulevard
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 05/17/2022