Flushing Meadows Corona Park Aquatic Center Emergency Netting System Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    78% complete

This project will install a debris netting system at Flushing Meadows Corona Park Aquatic Center.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020

Construction

Start Date: February 2020
Projected Completion Date: March 2020
Adjusted Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $7,300,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
131-04 Meridian Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/27/2020