Flushing Meadows Corona Park Aquatic Center Emergency Netting System Installation

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will install a debris netting system at Flushing Meadows Corona Park Aquatic Center.

Project Update: Design is complete.

Project Timeline

Design

Start Date: July 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
131-04 Meridian Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 01/28/2020