Flushing Meadows Corona Park Aquatic Center Emergency Netting System Installation
-
100% complete
-
100% complete
-
100% complete
This project will install a debris netting system at Flushing Meadows Corona Park Aquatic Center.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: July 2019
Projected Completion Date:
December 2019
Completion Date:
November 2019
Procurement
Start Date: November 2019
Projected Completion Date:
August 2020
Completion
Date:
February 2021
Construction
Start Date: February 2020
Projected Completion Date:
March 2020
Completion
Date:
July 2021
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Flushing Meadows Corona Park
, Queens
131-04 Meridian Road
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/01/2022