Flushing Meadows Corona Park Aquatic Center Emergency Netting System Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    8% complete

This project will install a debris netting system at Flushing Meadows Corona Park Aquatic Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2019
Projected Completion Date: December 2019
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020

Construction

Start Date: February 2020
Projected Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $7,300,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
131-04 Meridian Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 03/31/2020