Tappen Park Village Hall Roof Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the roof at the Village Hall located in Tappen Park. The work will include replacing or resetting slate roof tiles and chimney bricks; new gutters, skylights, flashing, and an access hatch; and repairing the dormer windows.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: Mayoral

Location

Tappen Park , Staten Island
111 Canal Street

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 05/07/2021