Bronx Park Skate Park Drinking Fountain Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct water service and a drinking fountain at the skate park in Bronx Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: February 2021

Procurement

Start Date: February 2021
Projected Completion Date: October 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Bronx Park , Bronx
Bronx Park East between Britton Avenue and Arnow Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/01/2021

Was this information helpful?