Linden Park Multipurpose Play Area Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the multipurpose play area at Linden Park.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: October 2020
Projected Completion Date:
October 2021
Completion Date:
November 2021
Procurement
Start Date: November 2021
Projected Completion Date:
August 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.