Crotona Park Indian Lake Shoreline Restoration

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees to restore the shoreline of Indian Lake in Crotona Park.

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2019
Projected Completion Date: September 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021
Completion Date: December 2022

Construction

Start Date: March 2023
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $575,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Crotona Park, Bronx
Crotona Avenue, Crotona Park North, Crotona Park East, Claremont Parkway
Community Board: 03

 

Project Staff

Contact NYC Parks about this project

Last updated: 04/18/2024

Was this information helpful?