Crotona Park Indian Lake Shoreline Restoration

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will remove invasive species and plant new and replacement trees to restore shoreline of Indian Lake in Crotona Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: August 2019
Projected Completion Date: September 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: September 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Borough President

Location

Crotona Park , Bronx
Crotona Avenue, Crotona Park North, Crotona Park East, Claremont Parkway

 

Project Staff

Contact NYC Parks about this project

Last updated: 12/04/2021

Was this information helpful?