Manhattan Beach Park Tennis Courts Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the tennis courts at Manhattan Beach Park.

Project Update: Parks is continuing to develop the documents to build this project and applying for necessary permits.

Project Timeline

Design

Start Date: September 2020
Projected Completion Date: September 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: City Council

Location

Manhattan Beach Park , Brooklyn
Oriental Boulevard at Mackenzie Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2021