Queensbridge Baby Park Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Queensbridge Baby Park.
Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.
Project Timeline
Design
Start Date: February 2022
Projected Completion Date:
May 2023
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Queensbridge Park
, Queens
North of Queensboro Bridge between Vernon Boulevard and 21st Street