Marine Park Oval Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the oval at Marine Park, including new asphalt pavement, drainage and water supply, drinking fountains, and benches.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: November 2020
Adjusted Completion Date: April 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Sources:
  • Mayoral
  • City Council

Location

Marine Park , Brooklyn
Avenue U, Stuart Street, Fillmore Avenue, East 33rd Street

 

Project Staff

Project Liaison: Davey Ives