Marine Park Oval Reconstruction
-
50% complete
-
0% complete
-
0% complete
This project will reconstruct the oval at Marine Park, including new asphalt pavement, drainage and water supply, drinking fountains, and benches.
Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.
Project Timeline
Design
Start Date: November 2019
Projected Completion Date:
November 2020
Adjusted Completion Date:
April 2021
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Marine Park
, Brooklyn
Avenue U, Stuart Street, Fillmore Avenue, East 33rd Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/26/2021