Marine Park Oval Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the oval at Marine Park, including new asphalt pavement, drainage and water supply, drinking fountains, and benches.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: November 2019
Projected Completion Date:
November 2020
Completion Date:
December 2021
Procurement
Start Date: December 2021
Projected Completion Date:
September 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Marine Park
, Brooklyn
Avenue U, Stuart Street, Fillmore Avenue, East 33rd Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 07/01/2022