Laurelton Playground Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Laurelton Playground.
Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.
Project Timeline
Design
Start Date: October 2020
Projected Completion Date:
January 2022
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Laurelton Playground
, Queens
Brookville Blvd between 136th and 138th Avenues
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 02/26/2021