This project will reconstruct the handball courts at Hallets Cove Playground.

Project Update: Design is complete.

Project Timeline

Design

Start Date: February 2020
Projected Completion Date: November 2020
Completion Date: September 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Borough President

Location

Hallets Cove Playground , Queens
Along East River, 1st Street, Astoria Blvd, and Vernon Blvd.

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 09/23/2020