Gorman Playground Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct Gorman Playground.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date:
December 2020
Procurement
Start Date: December 2020
Projected Completion Date:
August 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Gorman Playground
, Queens
84th Street, 85th Street, 25th Avenue, 30th Avenue
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 02/25/2021