Brooklyn Basketball Courts Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct basketball courts at Potomac Playground, Star Spangled Playground, and Taaffe Playground in Brooklyn.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: November 2019
Projected Completion Date:
May 2020
Completion Date:
September 2020
Procurement
Start Date: September 2020
Projected Completion Date:
May 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Potomac Playground
, Brooklyn
Tompkins Avenue & Halsey Street -
Star Spangled Playground
, Brooklyn
Franklin & Willoughby Avenues -
Taaffe Playground
, Brooklyn
Taaffee Place, Park & Myrtle Avenues
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/22/2021