Brooklyn Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct basketball courts at Potomac Playground, Star Spangled Playground, and Taaffe Playground in Brooklyn.

Project Update: Design is complete.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: May 2020
Completion Date: September 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 09/30/2020