Joe Michael's Mile Waterfront Structural Reconstruction (Hurricane Sandy)

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the waterfront Parks infrastructure damaged by Hurricane Sandy at Joe Michael's Mile.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: January 2022
Adjusted Completion Date: March 2023

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Location

Cross Island Parkway , Queens
Cross Island Parkway between Totten Avenue and 28th Avenue

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 08/12/2022