Manhattan Street Tree Planting FY21 - Community Boards 3, 6

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will plant new trees in Community Boards 3 and 6 in Manhattan.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

We are currently soliciting bids for this project. If you are interested in submitting a bid on this project, you can find the documents on our Bid Solicitations page.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Adjusted Completion Date: December 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020