Queens Street Tree Planting FY21 - Community Board 10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new trees in Community Board 10 in Queens.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $945,000
Funding Source: Mayoral

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 09/26/2022