Brooklyn Street Tree Planting FY21 - Community Boards 11, 13, 15

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 11, 13, and 15 in Brooklyn.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: August 2021

Construction

Start Date: October 2021
Projected Completion Date: October 2022
Completion Date: July 2022

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 08/10/2022