Brooklyn Street Tree Planting FY21 - Community Boards 1, 3, 4, 5, 16

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 1, 3, 4, 5, and 16 in Brooklyn.

Project Timeline

Design

Start Date: June 2019
Projected Completion Date: November 2019
Completion Date: September 2019

Procurement

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: August 2021

Construction

Start Date: August 2021
Projected Completion Date: August 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $2,990,000
Funding Sources:
  • City Council
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 07/01/2022