Van Cortlandt Park Skate Park Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a skate park in Van Cortlandt Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: November 2013
Projected Completion Date: June 2015
Completion Date: August 2015

Procurement

Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: April 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $1,178,000
Funding Sources:
  • Mayoral
  • City Council

Location

Van Cortlandt Park , Bronx
Broadway and Van Cortlandt Park South

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 09/29/2020