Manhattan Street Tree Planting FY20 - Community Board 4

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will plant new trees in Community Board 4 in Manhattan.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2020
Completion Date: February 2020

Procurement

Start Date: February 2020
Projected Completion Date: November 2020
Completion Date: November 2020

Construction

Start Date: April 2021
Projected Completion Date: July 2021

Understand how we build parks.

Funding

Total Funding: $93,000
Funding Source: Mayoral

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project