Manhattan Street Tree Planting FY20 - Community Board 4

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will plant new trees in Community Board 4 in Manhattan.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: May 2020
Completion Date: February 2020

Procurement

Start Date: February 2020
Projected Completion Date: November 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Various locations in Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020