Al Oerter Recreation Center, Constance Baker Motley Recreation Center & Chelsea Recreation Center HVAC Systems Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct the HVAC systems at Al Oerter Recreation Center, Constance Baker Motley Recreation Center, and Chelsea Recreation Center.
Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.
Project Timeline
Design
Start Date: March 2022
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Chelsea Recreation Center, Manhattan
Southside West 25 Street, 9 to 10 Avenues -
Constance Baker Motley Recreation Center, Manhattan
East 54th Street between 1st and 2nd Avenues. -
Flushing Meadows Corona Park, Queens
Grand Central Parkway, Van Wyck Expressway
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 06/30/2022