Flushing Meadows Corona Park Queens Storehouse Reconstruction

  • Design
    50% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the Queens Storehouse in Flushing Meadows Corona Park. The work will include reconstructing portions of the roof, exterior walls, and floor slab; new screening, signage, and a staging yard; and improved drainage and landscape restoration.

Project Update: Parks is continuing to develop the documents to build this project and applying for necessary permits.

Project Timeline

Design

Start Date: May 2020
Projected Completion Date: May 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
43 Meridian Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/17/2021