Jackie Robinson Recreation Center HVAC System Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the HVAC system at Jackie Robinson Recreation Center.

Project Update: Design is complete.

Project Timeline

Design

Start Date: April 2019
Projected Completion Date: October 2020
Completion Date: November 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Jackie Robinson Park , Manhattan
85 Bradhurst Avenue

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/19/2020