Bellerose Playground Reading Garden Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a reading garden at Bellerose Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: January 2021
Completion Date: January 2021

Procurement

Start Date: January 2021
Projected Completion Date: October 2021
Adjusted Completion Date: November 2022

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • State

Location

Bellerose Playground , Queens
85th Avenue between 248th Street and 249th Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 09/29/2022