Brooklyn Pavement Reconstruction (BG-1019M)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct pavements at various parks in Brooklyn.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: January 2020
Projected Completion Date: August 2020
Completion Date: December 2020

Procurement

Start Date: December 2020
Projected Completion Date: August 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Locations

  • Grand Army Plaza , Brooklyn
    Flatbush Avenue, Eastern Parkway and Prospect Park
  • Mount Prospect Park , Brooklyn
    Eastern Parkway, Flatbush Avenue between Underhill Avenue and Washington Avenue
  • Parade Ground , Brooklyn
    Caton, Coney Island, Parkside Avenues, Parade Place
  • Prospect Park , Brooklyn
    Prospect Park West, Flatbush, Parkside, Ocean Avenues
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/26/2021