Lopez Playground Modular Comfort Station Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a modular comfort station at Lopez Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2019
Projected Completion Date: November 2020
Completion Date: June 2021

Procurement

Start Date: June 2021
Projected Completion Date: February 2022
Completion Date: June 2022

Construction

Start Date: September 2022
Projected Completion Date: December 2023

Understand how we build parks.

Funding

Total Funding: $3,865,000
Funding Source: Mayoral

Location

Lopez Playground , Staten Island
Palma Drive between Targee Street and Oder Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/05/2022