Citywide Olympic Pool Mechanical Systems Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the mechanical systems at various Olympic pools citywide.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

  • Betsy Head Park , Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
  • CPL. Thompson Park , Staten Island
    Broadway, Henderso Avenue
  • Hamilton Fish Park , Manhattan
    Between East Houston & Stanton Streets
  • Highbridge Park , Manhattan
    West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
  • Jackie Robinson Park , Manhattan
    85 Bradhurst Avenue
  • Lyons Pool , Staten Island
    Murray Hulbert Avenue between Victory Boulevard and Hannah Street
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 08/14/2020