Citywide Olympic Pool Mechanical Systems Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the mechanical systems at various Olympic pools citywide.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: September 2019
Projected Completion Date:
January 2020
Completion Date:
January 2020
Procurement
Start Date: January 2020
Projected Completion Date:
October 2020
Adjusted Completion
Date:
August 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Betsy Head Park
, Brooklyn
Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street -
CPL. Thompson Park
, Staten Island
Broadway, Henderso Avenue -
Hamilton Fish Park
, Manhattan
Between East Houston & Stanton Streets -
Highbridge Park
, Manhattan
West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues -
Jackie Robinson Park
, Manhattan
85 Bradhurst Avenue -
Lyons Pool
, Staten Island
Murray Hulbert Avenue between Victory Boulevard and Hannah Street
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 02/25/2021