Citywide Olympic Pool Mechanical Systems Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the mechanical systems at various Olympic pools citywide.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: September 2019
Projected Completion Date: January 2020
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Locations

  • Betsy Head Park , Brooklyn
    Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
  • CPL. Thompson Park , Staten Island
    Broadway, Henderso Avenue
  • Hamilton Fish Park , Manhattan
    Between East Houston & Stanton Streets
  • Highbridge Park , Manhattan
    West 155th & Dyckman Streets, Edgecombe & Amsterdam Avenues
  • Jackie Robinson Park , Manhattan
    85 Bradhurst Avenue
  • Lyons Pool , Staten Island
    Murray Hulbert Avenue between Victory Boulevard and Hannah Street
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 06/03/2020