Kissena Corridor Park and Hutchinson River Parkway Path Lighting Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    75% complete

This project will construct pathway lighting at Kissena Corridor Park between 56th Avenue and Colden Street and at Hutchinson River Parkway along Bartow Avenue.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: January 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $798,000
Funding Sources:
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 09/29/2022