Kissena Corridor Park and Hutchinson River Parkway Path Lighting Construction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct pathway lighting at Kissena Corridor Park between 56th Avenue and Colden Street and at Hutchinson River Parkway along Bartow Avenue.

Project Update: A meeting was held with stakeholders to determine the scope of work for the project. Parks is now developing the design for the site.

Project Timeline

Design

Start Date: February 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 04/25/2019