Freshkills South Park Comfort Station Construction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a comfort station at Freshkills South Park.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million

Location

Freshkills Park , Staten Island
Arthur Kill Road at Muldoon Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 09/13/2019