Freshkills South Park Synthetic Turf Fields and Landscape Construction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands at Freshkills South Park.

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Freshkills Park , Staten Island
Arthur Kill Road at Muldoon Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 12/11/2019