Freshkills South Park Synthetic Turf Fields and Landscape Construction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct synthetic turf athletic fields, roadways, a parking lot with associated landscaping and stormwater management, multi-use and pedestrian paths, benches, signage, fencing, and lighting, and restore woodlands and wetlands at Freshkills South Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: December 2019
Adjusted Completion Date: December 2022

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Freshkills Park , Staten Island
Arthur Kill Road at Muldoon Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project