Monsignor Kett Playground Comfort Station Construction
-
100% complete
-
40% complete
-
0% complete
This project will construct a comfort station in Monsignor Kett Playground.
Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.
Project Timeline
Design
Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date:
August 2020
Procurement
Start Date: August 2020
Projected Completion Date:
May 2021
Adjusted Completion
Date:
October 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Monsignor Kett Playground
, Manhattan
West 204th Street between 10th Avenue and Nagle Avenue
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 08/09/2022