Sheltering Arms Playground Comfort Station Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Sheltering Arms Playground.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: February 2019
Projected Completion Date: February 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Sheltering Arms Playground , Manhattan
West 129th Street, Amsterdam Avenue, West 126th Street, Old Broadway

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/20/2019