Commodore Barry Park Comfort Station Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the comfort station in Commodore Barry Park.
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Start Date: April 2019
Projected Completion Date:
April 2020
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Commodore Barry Park
, Brooklyn
Flushing Avenue, North Elliot Place, Park Avenue and Navy Street
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 12/12/2019