Icahn Stadium Electrical Service Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    40% complete

This project will reconstruct the electrical service line from Icahn Stadium transformers to the PEP Academy trailer complex in Randall's Island.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2018
Projected Completion Date: February 2019
Completion Date: March 2019

Procurement

Start Date: March 2019
Projected Completion Date: December 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: October 2021

Understand how we build parks.

Funding

Total Funding: $1,987,000
Funding Source: Mayoral

Location

Randall's Island Park , Manhattan
Icahn Stadium to the PEP Academy trailer complex

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 07/27/2021

Was this information helpful?