Whitey Ford Field Seawall Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the seawall and waterfront infrastructure at Whitey Ford Field.
Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.
Project Timeline
Design
Start Date: October 2019
Projected Completion Date:
October 2021
Adjusted Completion Date:
October 2022
Procurement
The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Whitey Ford Field
, Queens
26th Avenue between 1st Street and 2nd Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 08/09/2022