Havemeyer Playground Comfort Station Reconstruction

  • Design
    35% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Havemeyer Playground.

Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.

Project Timeline

Design

Start Date: October 2018
Projected Completion Date: October 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Havemeyer Playground , Bronx
Watson Avenue between Havemeyer Avenue and East 177th Street

 