Captain Tilly Park Comfort Station Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Captain Tilly Park.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: November 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Captain Tilly Park , Queens
Highland Avenue between 165th Street and 166th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 01/17/2020