Captain Tilly Park Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the comfort station in Captain Tilly Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: November 2018
Projected Completion Date: November 2019
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: January 2022

Construction

Start Date: September 2022
Projected Completion Date: March 2024

Understand how we build parks.

Funding

Total Funding: $2,123,000
Funding Source: Mayoral

Location

Captain Tilly Park , Queens
Highland Avenue between 165th Street and 166th Street

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 06/28/2022